矿山充填体内预构巷道工艺方法研究
牛孝子,祝静骋,张 卓,丁 勇,龚自敏
((安徽金安矿业有限公司,霍邱 237474))
Study on the process method of prefabricated laneway in mine backfilling body
NIU Xiaozi, ZHU Jingcheng, ZHANG Zhuo, DING Yong, GONG Zimin
((Anhui Jin ''an mining Co., Ltd., Huoqiu Anhui 237474, China))
摘要
图/表
参考文献
相似文献
本文已被:浏览 292次   下载 247
投稿时间:2024-02-20    修订日期:2024-04-07
中文摘要: 目的:为解决阶段空场嗣后充填采矿法中二步骤矿柱采场开采面临充填体内开挖巷道支护量大、效率低、成本高的问题,实现二步骤矿柱采场出矿巷道快速成型。方法:本文针对国内某铁矿开展了充填体内预构巷道的工艺方法研究,采用调研、理论分析和试验的方法,分析预构载体在采场内的受力,进行预构载体的材料调研,选择橡胶充气芯模作为预构载体,结合矿山井下开采条件对橡胶充气芯模进行改造,设计了预构载体的布置方案,并开展了工业试验。结果:结果表明:采用橡胶充气芯模作为预构载体,一次充填高度不易超过2 m以避免橡胶充气芯模受到破坏。预构载体的尺寸确定需综合考虑巷道断面参数和预构载体的运输、安装等因素。与钻爆法在充填体内开挖巷道相比,采用橡胶充气芯模预构巷道可将施工效率提高近5倍,施工成本降低44%,并避免了钻爆法对充填体的破坏,降低了支护成本。意义:本文提出利用橡胶充气芯模作为预构载体,在一步骤采场充填前放置在预形成巷道处,待充填体凝固后收缩橡胶芯模而形成巷道,研究成果对国内类似矿山具有借鉴意义。
Abstract:Purpose: In order to solve the problems of large support amount, low efficiency and high cost of excavation laneway in backfill in the two-step stope mining of open stoping with subsequent backfilling method and to realize the purpose of rapid prototyping of the mining laneway in the two-step pillar stope, this paper carried out process method research on the pre-formed laneway in backfill for an iron mine in China. Method: The methods of investigation, theoretical analysis and experiment were adopted. By analyzing the force of the preformed carrier and conducting material research on the preformed carrier, rubber pneumatic bag was selected as the preformed carrier. Based on the underground mining conditions, the prefabricated carrier layout scheme was designed and the industrial test was carried out. Result: The experimental results show that the filling height shouldn’t exceed 2 m at a time when using rubber pneumatic bag as the preformed carrier to avoid damage, that the dimension determination of the prefabricated carrier should consider the laneway section parameters and the transportation and installation of the prefabricated carrier, and that the construction efficiency can be increased by nearly 5 times and the construction cost can be reduced by 44% compared with drilling and blasting method. The damage to the backfill body can be avoided by drilling and blasting method, and the support cost can be reduced. Significance: In this paper, rubber pneumatic bag is used as a preformed carrier, which is placed in the pre-formed laneway before the one-step stope backfilling, and shrinks the rubber pneumatic bag to form laneway after the filling slurry solidified. The research results can be used as reference for similar mines in domestic.
文章编号:     中图分类号:    文献标志码:
基金项目:
引用文本:
牛孝子,祝静骋,张 卓,丁 勇,龚自敏.矿山充填体内预构巷道工艺方法研究[J].有色金属(矿山部分),2024,76(5):171-177,192.
NIU Xiaozi,ZHU Jingcheng,ZHANG Zhuo,DING Yong,GONG Zimin.Study on the process method of prefabricated laneway in mine backfilling body[J].NONFERROUS METALS(Mining Section),2024,76(5):171-177,192.

我们一直在努力打
造,精品期刊,传
播学术成果

全国咨询服务热线
86-10-63299757

杂志信息

期刊简介

相关下载

联系我们

电话:010-63299757

传真:010-63299754

QQ:XXXXXXX

Email:ysjsks@sina.com;ysjsks@163.com

邮编:100160

地址:北京市南四环西路188号总部基地十八区23号楼

关注微信公众号