本文已被:浏览 989次 下载 25次
中文摘要: 针对某大型金铜矿床开采现状,采取挖潜、技改、扩能等措施,实现全露天开采并达到年产黄金16t,铜矿2×10^4t/d矿石规模,最大采剥总量达85×10^ 6t/a,并能充分回收低品位金铜矿资源,使企业效益最佳.
Abstract:On the basis of the exploitation actuality of a large-scale gold-copper deposit, the technical measures are suggested such as utilizing the potential reserves, conducting the technological transformations and increasing productivity to realize full opencast mining, and achieve a mining scale with gold of 16 t/a, copper ore of 20 000 t/d, total mining and overburden amount of 85 Mt/a. Therefore, low-grade gold-copper resources can be fully recovered and the mine obtains the best benefit.
文章编号: 中图分类号:TD863 文献标志码:
基金项目:
高祥
南昌有色冶金设计研究院,江西南昌330002
Gao Xiang
Nanchang Engineering and Research Institute of Nonferrous Metals
引用文本:
高祥.浅谈某大型金铜矿床联合开采[J].有色金属(矿山部分),2007,59(4):1-4.
.On Combined Mining of a Large-scale Gold-copper Deposit[J].NONFERROUS METALS(Mining Section),2007,59(4):1-4.
高祥.浅谈某大型金铜矿床联合开采[J].有色金属(矿山部分),2007,59(4):1-4.
.On Combined Mining of a Large-scale Gold-copper Deposit[J].NONFERROUS METALS(Mining Section),2007,59(4):1-4.